Wasserrechtliche Bewilligung (water rights permit)
Anyone using groundwater for a heat pump requires a wasserrechtliche Bewilligung (water rights permit). Geothermal energy is only affected in certain cases, in which case a notification is required.
- Deep drilling: probes reach vertically deep into the ground.
- Horizontal collector: pipes lie horizontally just below the surface and require a lot of garden space.
- Groundwater: one well extracts water, a second one returns it.
The Wasserrechtsgesetz 1959 (WRG, Water Rights Act) applies nationwide across Austria. It regulates when you need the water rights authority for a groundwater heat pump or a geothermal energy system. Building law in the federal states must be checked separately.
Why this is important
- Groundwater: Without a permit, according to Section 10(1), only the necessary domestic and agricultural requirements of the landowner are allowed. In all other cases, a permit is required (Section 10(2)). Groundwater heat pumps always require a permit according to the State of Upper Austria. According to the State of Carinthia, this also applies to returning water into the subsoil (Section 32(2)(b)).
- Geothermal energy: Section 31c(5) covers systems in areas with special water rights protection and in built-up settlement areas without a central drinking water supply. Deep probes are also included if they extend deeper than 300 m or are located in areas with confined groundwater.
- Notification procedure (Anzeigeverfahren): You must notify the authority of these geothermal systems three months before construction begins with project documentation (Section 114). If the authority does not request a formal permit procedure in writing within three months, the permit is deemed granted. It is limited to 25 years from the date of submitting the notification.
The responsible authority is usually the district administrative authority (Bezirksverwaltungsbehörde, Section 98), i.e. Bezirkshauptmannschaft (district commission) or Magistrat (municipal authority). In Carinthia, according to the information sheet, systems up to 5 l/s go there, and above that to the state government.
What this means for you
- Before planning, check with the authority to see whether your plot of land is affected.
- Procedures differ depending on the federal state. The authority will tell you which documents it requires.
- In the notification procedure, allow for at least three months before construction begins.
You can find the requirements for each federal state under Permits and approvals, for technical details see Deep drilling.
Related terms
Water-to-water heat pump (groundwater)Deep drilling (geothermal probe)Surface collector (ground collector)Brine-to-water heat pump (geothermal)
Sources
- Wasserrechtsgesetz 1959 (RIS), Sections 10, 31c, 98 and 114 (retrieved on 4 November 2026)
- Land Oberösterreich: Heat pumps (water rights regulations) (retrieved on 4 November 2026)
- Office of the Carinthian State Government: Groundwater heat pump information sheet (as of October 2018) (retrieved on 4 November 2026)